In July 2004 CAE completed the take over of Sutherland Engineers Ltd making them the only Pump distributor in Scotland who own and operate their own Pipework and vessel fabricator without the need to subcontract and incur the unnecessary cost of outside contractors.
Now based in our state of the art manufacturing facility in Clydebank we offer clients a full project management service & the ability to design, specify, supply & install any kind of fluid handling system. In doing so we have demonstrated the benefits of:

1. Customised design to suit our clients specific requirements.
2. One point of contact for the client.
3. Reducing our clients supply chain.
4. Easy expediting.
5. Cost effective.
6. Co-ordinated project management.

Tanks & Pressure Vessels

tanks and pressure vessels

From 0.1 to 150m3 vessel size in a variety of material specifications that can be open to atmosphere or pressure rated and designed specifically to meet our clients
requirements.

Steam & Boiler Pipework

steam and boiler pipework

Fully coded and certified steam & boiler Pipework manufactured to the most exacting standards BS , DIN , ASME.

Pump,Tank & Filter Installations

pump, tank and filter installations

Clyde are one of Scotlands largest pump distributors and are the only supplier to have their own dedicated Pipework /
fabrication division and are thus ideally placed to offer pump / filter / Pipework installations as a turnkey project.

pump, tank and filter installations

 

Hygienic & CIP Pipework Systems

hygenic and cip pipework systems

The company has developed a reputation over a 25 year period for excellence in hygienic applications where highest standards of cleanliness are required in the food & drink, pharmaceutical & biotech industries.

Heat Recovery System

Designed by our in house projects team to suit customers specific applications.

heat recovery systems

Turnkey Projects
Vat Installation Project

In 2005 we undertook a project whose aim was to move 2 off 120,000 litre stainless steel VATs from Kilwinning in Ayrshire to Dalmuir Bond. This project was challenging on a number of fronts.

1) SIZE - These are large Vats measuring 5.5M high by 5M diameter.
2) LOGISTICS - The Vats were de-installed from a bond in Kilwinning and transported to the new site via low loader transport.
3) SITE CONSTRAINTS - The Vats were offloaded at site and moved into place. The key project objective was to ensure that they fitted into the existing space restraints of the new site.
4) PROJECT INSTALLATION - Once the Vats were moved into place all the following was specified, supplied and installed by Sutherland Engineers:
1. Pumps
2. Valves
3. Pipework
4. Filtration

vat installation project

vat installation project

vat installation project

vat installation project

vat installation project

Re-Slurry Project
We recently completed a slurry recycle project for a distillery in Edinburgh. Sutherland specified, supplied and installed:
1. 1off Slurry vessel.
2. 1off Slurry recycle pot.
3. 6off Durco ANSI Mk3 pumps.
4. All interconnecting pipework.
5. All process valves.
6. Stainless steel flooring.

north british project

north british project

north british project

north british project

north british project

Clyde Associated Engineers Ltd, 76 Beardmore Way, Clydebank Industrial Estate, Glasgow, G81 4HT, Tel: 0141 951 1331, Fax: 0141 951 3460
Registered in Scotland No. 29048 All site content © Clyde Associate Engineers.